Joseph Reed Gets a Face Lift

Posted on July 15th, 2014 by achang

Posted under: _Melbourne School of Design, construction

The Historic Facade of the Bank of New South Wales is an essential element of, what is lovingly called, The Concrete Lawn.  In the competition stage teams struggled with whether to relocate it or to integrated it into the new FABP  building.  We chose the latter.

 

220811_02

JOSEPH REED’S BANK OF NEW SOUTH WALES FACADE  PRE-DEMOLITION 

OLYMPUS DIGITAL CAMERA

APRIL 2013 – HISTORIC FACADE BRACED

OLYMPUS DIGITAL CAMERA 

JULY 2013 – EVERYTHING BUT JOSEPH REED IS DEMOLISHED

photo (6)

DEC 2013 – PRIMARY STRUCTURE ERECTED

photo (8)

JUNE 2014 – DRYWALL FRAMING

FABP_July2014_20

JULY 2014 – DRYWALL ALMOST COMPLETE….

jreed_20140715_03

JULY 2014 – FIRST COAT

OLYMPUS DIGITAL CAMERA

Comments Off on Joseph Reed Gets a Face Lift

MASONRY SURGERY + TIMBER PROSTHETICS

Posted on June 24th, 2014 by tberesford

Posted under: construction

dfald_libraryView1_highRes

Another dispatch from the ongoing Phase I renovation of Knox College at 1 Spadina Crescent for the University of Toronto Daniels Faculty of Architecture, Landscape and Design.   Structural masonry retrofit work is costly, and NADAAA has endeavoured to avoid it wherever possible in the project.  Nevertheless, there were several locations where the requirements of the program, security or new building services have necessitated masonry removal and the installation of steel lintels to transfer loads bearing down from above.  Depending on the lintel’s span/size of opening below, the shoring work required to stabilize loads above can be complex and time-consuming.

ABOVE RIGHT:  NADAAA rendering of the new library study room, complete with new masonry opening to suit a service counter and clear site-lines from the adjacent library workroom, as required by the client’s program.  (see rectangular opening adjacent to the existing arched doorway).

 

IMG_9986

ABOVE: Needle shoring was required to stabilize the loads above for work to proceed: masonry demolition and installation of the permanent steel w-section lintel for this 3.5 meter wide opening. “Needling” gets its name from the (in this case aluminum) structural sections penetrating the masonry, and resting on shores at either side of the wall.

 

f-29.dan-14-32a

ABOVE: Inspection of the building’s original sawn timber joists by a wood specialist uncovered the need to reinforce the floor assembly to achieve code compliance in many locations. This was accomplished either by sistering steel c-channels to each individual joists (thereby maintaining maximum ceiling clearance), or through the installation of a new steel girder below mid-span of the joists, as shown above.  (photo courtesy Peter MacCallam / The Daniels Faculty)

 

Untitled-11

ABOVE LEFT: The wood consultant also identified the need for reinforcement of two monumental timber trusses that support the attic and roof above the central block on the top level.  Entuitive, our structural engineer, provided steel plate strapping, bolted to either side of the cracked bottom timber cords in response to the wood consultant recommendations.   (sketches courtesy Entuitive Corporation).  ABOVE LEFT: An original building section drawing dated 1873 shows the referenced space and trusses, which flank the central masonry tower. (courtesy U. of Toronto archive.

 

IMG_0088

ABOVE: The timber trusses, after installation of steel plate strapping. These will be painted a uniform color. The clear span allows this feature space to support various configurations of graduate studios and student exhibition/crit space over the course of the phased project.

 

 

Comments Off on MASONRY SURGERY + TIMBER PROSTHETICS

Construction Update in 5 Minutes

Posted on June 20th, 2014 by Sia Herr

Posted under: _Melbourne School of Design, construction

Check out the  time-lapse construction video of  University of Melbourne’s Faculty of Architecture, Building and Planning from January 2013 – April 2014.  Only a couple more months until we get to see the completed building.

Additional  videos from different cameras on-site are also available on the university’s website.

 

 

Comments Off on Construction Update in 5 Minutes

Reinstating the Convocation Hall

Posted on June 16th, 2014 by tberesford

Posted under: construction

 

Phase I renovation of Knox College at 1 Spadina Crescent is progressing for the University of Toronto Daniels Faculty of Architecture, Landscape and Design.  Currently, demolition, restoration and structural work is underway at the former original Convocation Hall, which forms the east wing of the neo-gothic structure.  The monumental triple-height volume of the hall had been subdivided into three floors during  19040’s era alterations to suit the needs of the former Connaught laboratories.  The current renovation calls for a double-height space to be carved out of the second level, with intent to at least partially reinstate the grandeur of the original hall.

IMG_0069

ABOVE: Ongoing demolition and structural retrofit to the fomer Convocation Hall at Knox College / 1 Spadina Crescent.  The original timber trusses have been exposed at level 03 as seen beyond.  The Level 03 floor structure in the foreground has been removed in preparation for shoring to support a new composite mezzanine floor.  Steel moment frames have been installed where some of the original timber trusses were removed.  The moment frames serve to stabilize lateral forces on the building while also retaining the open floor clearance at the level 03 mezzanine.  The level 03 floor seen beyond in the image above will be removed after the mezzanine slab is poured.  In the foreground, walls added in the 1940s that supported storage vault rooms and a stair are being removed.

 

Untitled-1

ABOVE LEFT: Original sectional drawing of the Knox college convocation hall (1873). ABOVE RIGHT: The convocation hall in its original condition.  The timber hips shown below the timber trusses were removed when the hall was subdivided into three floors.

 

IMG_0048

ABOVE: this image was taken from level 02, below the floor structure that was demolished in preparation for the new level 03 mezzanine structure. This space was also flanked by a stair and a series of storage vaults, both of which have been removed.  The bottom cord of the original timber truss in this zone has truncated/sawn in this location, and a pair of c-channel moment frames have been sistered to either side of the upper cord.

 

Document1 Page 004

ABOVE: A structural detail indicating the retrofit c-channel moment frames, and the new composite mezzanine slab. (courtesy Entuitive Corporation)

 

IMG_0066

ABOVE: A detail of the original timber truss top cord, with sistered c-channel moment frames installed at either side.

 

Document1 Page 003

ABOVE: Sketch indicating retrofits to repair damaged timber trusses at the east end of the former convocation hall. The original trusses will be featured in this location upon removal of the existing level 03 wood floor structure. This sketch documents steel tension rods that have been installed to relieve forces on the existing timber ties (which have sustained cracks/damage over the years).  (courtesy Entuitive Corporation)

 

IMG_0055

ABOVE: Detail showing steel rod reinforcement installed to reinforce the bottom ord of the original timber trusses. The level 03 floor structure on either side will be removed to open a double-height space, reminiscent of the original convocation hall.  Original hip support to the bottom of truss had been removed at the time of previous renovation.

 

Comments Off on Reinstating the Convocation Hall

Taking Shape

Posted on May 14th, 2014 by Sia Herr

Posted under: construction, Installations + Exhibitions

Construction of NoMa art installation has begun.  Stay tuned for the final photos!

noma03

noma04

noma02

Comments Off on Taking Shape

Nearing Completion

Posted on May 12th, 2014 by Sia Herr

Posted under: _Melbourne School of Design, construction

The construction of the University of Melbourne FABP has been very exciting and we are glad to see it actively documented through time lapse cameras, a university blog and video series. The latest video by the university captures John Wardle and Nader Tehrani’s visit to the site as the building nears completion. We can’t wait to share the finished project.

JWA and NADAAA in collaboration.
Visit the University of Melbourne blog: http://abp.unimelb.edu.au/blog
Check out the timelapse: http://www.abp.unimelb.edu.au/timelapse

Comments Off on Nearing Completion

Melbourne Milestones

Posted on March 10th, 2014 by Sia Herr

Posted under: _Melbourne School of Design, construction

Over the last month, construction of Melbourne University FABP celebrated two major milestones. One being the removal of the supports for the 40 foot cantilever and the other, the installation of the coffered roof which has been an intricate and coordinated process to bring on site and install.  You can already start to experience the spatial impact of these two elements.

UMBcantilever1

UMBextrendering

UMBglassroof1

UMBcoffer1

JWA and NADAAA in collaboration.

Comments Off on Melbourne Milestones

For Our Own Home

Posted on February 21st, 2014 by pmacdowell

Posted under: construction, Installations + Exhibitions, NADLAB

Unable to find suitable stands for our architectural models, we commissioned ourselves to build a custom set of steel tables.

modelStands00Each table has a simple frame of 1″ square tube. The steel is cut to length with double-bevels (yay for our new lubricated band saw), jigged square, and tacked together.

modelStands01aResolving the corners of the implied box is the key detail of the design. The cleanly-executed welds are left unground and exposed.

modelStands02The frames are topped with a raw 3/16″ plate and fitted with leveling/locking casters.

modelStands03Our models, in the NADAAA gallery space.

Comments Off on For Our Own Home

Coffered Roof Taking Shape

Posted on February 5th, 2014 by Sia Herr

Posted under: _Melbourne School of Design, construction

Last week, we posted on the off-site fabrication of the panels for the coffered roof above the studio hall at the University of Melbourne.  The first bay has been assembled and craned in place!  Stay tuned for the full reveal.

umbcoffer1

umbcoffer2

umbcoffer3

JWA in collaboration with NADAAA.  Photo credit: JWA

Comments Off on Coffered Roof Taking Shape

Melbourne Coffered Roof

Posted on January 27th, 2014 by Sia Herr

Posted under: _Melbourne School of Design, construction

The glu-lam coffers at University of Melbourne are being prefabricated off-site and prepared for installation. Each module differs in dimensions, faceted to integrate with the suspended studio.

umblvl01umblvl03

umb

OLYMPUS DIGITAL CAMERAumblvl05

umblvl022

JWA in collaboration with NADAAA.  Photo credit: JWA

Comments Off on Melbourne Coffered Roof